25 Sep 26
MOL has completed construction work on the fire-damaged AV3 crude distillation unit at its Danube refinery in Hungary, according to its 22 September stock-exchange disclosure.
The company said the project was completed according to schedule and the unit will now move through commissioning and testing before crude oil is introduced. Production is scheduled to restart gradually during October, after which the Százhalombatta refinery is expected to return to full capacity.
The restoration budget totalled HUF 18 billion. Work following the October 2025 fire included rebuilding damaged reinforced-concrete structures, restoring process and electrical equipment, installing 27 new pumps, replacing eight kilometres of piping and laying around 100 kilometres of electrical cable.
Before restart, MOL will flush and pressure-test the systems, test process-control and safety equipment and coordinate AV3 with associated refinery units.
GC Intelligence provides independent European polymer price intelligence across engineering resins, styrenics and commodity polymers, generated through direct conversations with market participants. If your organisation requires an independent pricing reference, price forecasts and first-hand insight into current market developments, enquire about access.